To: Sam Okafor
Subject: This week: 2 projects need a look
Projects
- Slipping: New salt dome at the yard (forecast December 2 is after the November 27 target)
- At risk: Lakeview Condos retaining wall (1 task overdue)
- On track: Snow season ready (forecast November 28, target November 30)
- On track: Spring early-booking campaign (forecast January 10, target January 15)
Overdue
- Get three quotes for the salt dome (Morgan Hale, due November 9)
- Send the condo board the drainage change for approval (Grace Lin, due November 10)
Done this week
- Update the snow contract prices (+6%)
Decided this week
- The salt dome pad isn't poured until the contractor is chosen.